Price escalation of unit rate for construction works of brick wall & boundary wall
This variation order has been made between Brac University and BUCG-ABC joint venture for price escalation of unit rate for construction works of brick wall & boundary wall of Brac University new campus project.
第一著者: | NS Construction Ltd. |
---|---|
フォーマット: | Variation order |
言語: | English |
出版事項: |
Brac University
2023
|
主題: | |
オンライン・アクセス: | http://hdl.handle.net/10361/21160 |
類似資料
-
Approval unit rate for construction of architectural brick wall
著者:: NS Construction Ltd.
出版事項: (2023) -
Price escalation of unit rate for construction works of brick wall and boundary wall of NS Construction due to unusual increase of construction material price
著者:: Brac University
出版事項: (2023) -
Approval of price escalation for internal plumbing & sanitary works
著者:: BUCG-ABC Joint Venture (BUCG-ABC JV)
出版事項: (2023) -
Construction schedule for brick wall mock-up of BRAC University new campus project
著者:: BUCG-ABC Joint Venture (BUCG-ABC JV)
出版事項: (2023) -
Approval of price escalation for aluminum windows by BUCG
著者:: BUCG-ABC Joint Venture (BUCG-ABC JV)
出版事項: (2023)