Approval of rate for punch through concrete slab for the condensate drain pipe for each HAHU of the classroom
This variation order has been made between Brac University and BUCG-ABC joint venture for approval of rate for punch through concrete slab for the condensate drain pipe for each HAHU of the class room of Brac University new campus project.
Autor principal: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Formato: | Variation order |
Lenguaje: | English |
Publicado: |
Brac University
2023
|
Materias: | |
Acceso en línea: | http://hdl.handle.net/10361/21105 |
Ejemplares similares
-
Punch through concret slab for the condensate drain pipe for each HAHU of the calss room
por: BUCG-ABC Joint Venture (BUCG-ABC JV)
Publicado: (2023) -
Purchase order for punch through concrete slab for the condensate drain pipe for each HAHU of the classroom for BracU new campus project
por: Brac University
Publicado: (2023) -
Purchase order for supply & installation of precast concrete slabs on the pedestals for the roof drainage of BRACU new campus project
por: Brac University
Publicado: (2023) -
Observation regarding the concrete surface quality of roof slab & preparation of mock-up
por: Brac University
Publicado: (2023) -
Missing of punches for MEP works in the concrete members (slab, beam & walls)
por: Brac University
Publicado: (2023)