Punch through concret slab for the condensate drain pipe for each HAHU of the calss room

This variation order has been made between Brac University and BUCG-ABC joint venture for Punch through concrete slab for the condensate drain pipe for each HAHU of the class room of Brac University new campus project.

Detalles Bibliográficos
Autor principal: BUCG-ABC Joint Venture (BUCG-ABC JV)
Formato: Variation order
Lenguaje:English
Publicado: Brac University 2023
Materias:
Acceso en línea:http://hdl.handle.net/10361/21102