The engineer's instruction for rectification of opening for escalator in grid 'X, 19-20 & W, 19-20' of B1 to B1(A)
This record consists of general correspondence regarding the engineer's instruction for rectification of opening for escalator in grid 'X, 19-20 & W, 19-20' of B1 to B1(A) of BRAC University new campus project.
主要作者: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
格式: | General correspondence |
語言: | English |
出版: |
Brac University
2023
|
主題: | |
在線閱讀: | http://hdl.handle.net/10361/20452 |
相似書籍
-
The engineer’s Instruction for rectification of opening for escalator in grid ‘X, 19-20 & W, 19-20’ of B1 to B1 (A-)
由: Brac University
出版: (2023) -
Instruction to do beam rectification work as per WEB sketch (SK125)
由: BUCG-ABC Joint Venture (BUCG-ABC JV)
出版: (2023) -
Rectification of the PF value
由: BUCG-ABC Joint Venture (BUCG-ABC JV)
出版: (2023) -
Regarding the deviation in the groove making & pit width at north zone escalator
由: Brac University
出版: (2023) -
Rectification of D-Wall
由: Brac University
出版: (2023)