Response to the engineer’s reply concerning evaluation for additional work of sharing pile work in zone B
This record consists of general correspondence regarding the response to the engineer’s reply concerning evaluation for additional work of sharing pile work in zone B of BRACU new campus development project.
Huvudupphovsman: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Materialtyp: | General correspondence |
Språk: | English |
Publicerad: |
Brac University
2023
|
Ämnen: | |
Länkar: | http://hdl.handle.net/10361/20408 |
Liknande verk
-
Evaluation for additional work of shoring pile work in zone B
av: BUCG-ABC Joint Venture
Publicerad: (2023) -
Evaluation for additional work of shoring pile work in zone B
av: BUCG-ABC Joint Venture (BUCG-ABC JV)
Publicerad: (2023) -
Evaluation for additional work of shoring pile work between zone B
av: Brac University
Publicerad: (2023) -
Evaluation for additional work of sharing pile work between zone A and zone C – 05.04.18
av: BUCG-ABC Joint Venture (BUCG-ABC JV)
Publicerad: (2023) -
Evaluation for additional work of shoring pile work between zone A and C
av: Brac University
Publicerad: (2023)