Flush valve issue causing delay of the plumbing works as well as tiling works for the bath rooms in BRACU NCP
This record consists of general correspondence regarding the flush valve issue that caused delay of the plumbing works as well as tiling works for the bath rooms in BRACU new campus project.
主要作者: | Brac University |
---|---|
格式: | General correspondence |
语言: | English |
出版: |
Brac University
2023
|
主题: | |
在线阅读: | http://hdl.handle.net/10361/20013 |
相似书籍
-
Replacement of the defective flush valve
由: Brac University
出版: (2023) -
Decision of BRACU authority about the defective flush valves supplied by Tilottoma
由: Brac University
出版: (2023) -
Completion of pressure testing, rectification and replacement of the defective spare parts of the supplied and installed flush valves
由: Brac University
出版: (2023) -
Instruction to replace all the flash valves of the WC
由: Brac University
出版: (2023) -
Letter of flush valve replacement
由: Tillotoma Gulshan