Time-To-Build and Convex Adjustment Costs /
This paper incorporates time-to-build into the standard investment model with convex adjustment costs. The empirical Euler equation is estimated using a U.S. firm-level panel from Compustat. In spite of the introduction of time-to-build, the magnitude of the implied adjustment costs is unrealistical...