Time-To-Build and Convex Adjustment Costs /

This paper incorporates time-to-build into the standard investment model with convex adjustment costs. The empirical Euler equation is estimated using a U.S. firm-level panel from Compustat. In spite of the introduction of time-to-build, the magnitude of the implied adjustment costs is unrealistical...

Täydet tiedot

Bibliografiset tiedot
Päätekijä: Koeva Brooks, Petya
Aineistotyyppi: Aikakauslehti
Kieli:English
Julkaistu: Washington, D.C. : International Monetary Fund, 2001.
Sarja:IMF Working Papers; Working Paper ; No. 2001/009
Linkit:Full text available on IMF