Issue about finishing the floor works on 4th & 5th floor
This record consists of general correspondence regarding the issue about finishing the floor works on 4th & 5th floor of BRACU new campus building.
Príomhchruthaitheoir: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Formáid: | General correspondence |
Teanga: | English |
Foilsithe / Cruthaithe: |
Brac University
2023
|
Ábhair: | |
Rochtain ar líne: | http://hdl.handle.net/10361/20742 |
Míreanna comhchosúla
Míreanna comhchosúla
-
5th floor decking slab
de réir: WOHA Designs PTE LTD, et al.
Foilsithe / Cruthaithe: (2023) -
4th floor decking slab
de réir: WOHA Designs PTE LTD, et al.
Foilsithe / Cruthaithe: (2023) -
Time extension of design change for 6th-8th floor
de réir: BUCG-ABC Joint Venture (BUCG-ABC JV)
Foilsithe / Cruthaithe: (2023) -
Time extension of design change for 6th-8th floor
de réir: BUCG-ABC Joint Venture (BUCG-ABC JV)
Foilsithe / Cruthaithe: (2023) -
Joint details between facade and floor finishes (classroom, 9th storey) (RFA-575_Rev.A)
de réir: BUCG-ABC Joint Venture (BUCG-ABC JV)
Foilsithe / Cruthaithe: (2023)