Substation of claim from 23th April 2018 to 30th June 2018 due to defective diaphragm wall
This record consists of general correspondence regarding the substation of claim from 23th April 2018 to 30th June 2018 due to defective diaphragm wall of Brac University new campus development project .
Hovedforfatter: | BUCG-ABC Joint Venture |
---|---|
Format: | General correspondence |
Sprog: | English |
Udgivet: |
Brac University
2023
|
Fag: | |
Online adgang: | http://hdl.handle.net/10361/20513 |
Lignende værker
-
Substation of claim from 26 february 2018 to 25 March 2018 due to defective fiaphragm – 04.04.18
af: BUCG-ABC Joint Venture
Udgivet: (2023) -
Submission of claim from 26th March 2018 t0 22nd April 2018 due to diaphragm wall
af: BUCG-ABC Joint Venture (BUCG-ABC JV)
Udgivet: (2023) -
Substantiation of claims diaphragm wall
af: BUCG-ABC Joint Venture
Udgivet: (2023) -
Additional wall attached to diaphragm wall
af: BUCG-ABC Joint Venture (BUCG-ABC JV)
Udgivet: (2023) -
Request of certifying compensation submitted due to defect D-wall