Substation of claim from 23th April 2018 to 30th June 2018 due to defective diaphragm wall
This record consists of general correspondence regarding the substation of claim from 23th April 2018 to 30th June 2018 due to defective diaphragm wall of Brac University new campus development project .
主要作者: | BUCG-ABC Joint Venture |
---|---|
格式: | General correspondence |
语言: | English |
出版: |
Brac University
2023
|
主题: | |
在线阅读: | http://hdl.handle.net/10361/20513 |
相似书籍
-
Substation of claim from 26 february 2018 to 25 March 2018 due to defective fiaphragm – 04.04.18
由: BUCG-ABC Joint Venture
出版: (2023) -
Submission of claim from 26th March 2018 t0 22nd April 2018 due to diaphragm wall
由: BUCG-ABC Joint Venture (BUCG-ABC JV)
出版: (2023) -
Substantiation of claims diaphragm wall
由: BUCG-ABC Joint Venture
出版: (2023) -
Additional wall attached to diaphragm wall
由: BUCG-ABC Joint Venture (BUCG-ABC JV)
出版: (2023) -
Request of certifying compensation submitted due to defect D-wall
由: BUCG-ABC Joint Venture