The engineer's instruction for rectification of opening for escalator in grid 'X, 19-20 & W, 19-20' of B1 to B1(A)
This record consists of general correspondence regarding the engineer's instruction for rectification of opening for escalator in grid 'X, 19-20 & W, 19-20' of B1 to B1(A) of BRAC University new campus project.
Κύριος συγγραφέας: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Μορφή: | General correspondence |
Γλώσσα: | English |
Έκδοση: |
Brac University
2023
|
Θέματα: | |
Διαθέσιμο Online: | http://hdl.handle.net/10361/20452 |
Παρόμοια τεκμήρια
-
The engineer’s Instruction for rectification of opening for escalator in grid ‘X, 19-20 & W, 19-20’ of B1 to B1 (A-)
ανά: Brac University
Έκδοση: (2023) -
Instruction to do beam rectification work as per WEB sketch (SK125)
ανά: BUCG-ABC Joint Venture (BUCG-ABC JV)
Έκδοση: (2023) -
Rectification of the PF value
ανά: BUCG-ABC Joint Venture (BUCG-ABC JV)
Έκδοση: (2023) -
Regarding the deviation in the groove making & pit width at north zone escalator
ανά: Brac University
Έκδοση: (2023) -
Rectification of D-Wall
ανά: Brac University