Response to engineer's letter Ref. BRACU-NCP-2018 25A & 26A
This record consists of general correspondence regarding response to engineer's letter Ref. BRACU-NCP-2018 25A & 26A of BRACU new campus development project.
1. autor: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Format: | General correspondence |
Język: | English |
Wydane: |
Brac University
2023
|
Hasła przedmiotowe: | |
Dostęp online: | http://hdl.handle.net/10361/20443 |
Podobne zapisy
-
Request for letter of authority
od: BUCG-ABC Joint Venture (BUCG-ABC JV)
Wydane: (2023) -
The Interim application of EOT from 23” April, 2018 to 20''‘ map 2018 our Ref: BUCG-ABC JV-JAA-014
od: BUCG-ABC Joint Venture
Wydane: (2023) -
Substation of claim from 26 february 2018 to 25 March 2018 due to defective fiaphragm – 04.04.18
od: BUCG-ABC Joint Venture
Wydane: (2023) -
Reminder for immediate response of the engineer's representative team
od: BUCG-ABC Joint Venture (BUCG-ABC JV)
Wydane: (2023) -
Letter about income tax return problem for short challan
od: BUCG-ABC Joint Venture (BUCG-ABC JV)
Wydane: (2023)