Submission of claim from 26th March 2018 t0 22nd April 2018 due to diaphragm wall
This record consists of general correspondence regarding the submission of claim from 26th March 2018 t0 22nd April 2018 due to diaphragm wall of BRACU new campus development project.
Auteur principal: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Format: | General correspondence |
Langue: | English |
Publié: |
Brac University
2023
|
Sujets: | |
Accès en ligne: | http://hdl.handle.net/10361/20370 |
Documents similaires
-
Substantiation of claims diaphragm wall
par: BUCG-ABC Joint Venture
Publié: (2023) -
Substation of claim from 23th April 2018 to 30th June 2018 due to defective diaphragm wall
par: BUCG-ABC Joint Venture
Publié: (2023) -
Substation of claim from 26 february 2018 to 25 March 2018 due to defective fiaphragm – 04.04.18
par: BUCG-ABC Joint Venture
Publié: (2023) -
Additional wall attached to diaphragm wall
par: BUCG-ABC Joint Venture (BUCG-ABC JV)
Publié: (2023) -
Substantiation of claims of diaphragm wall of BRAC University new campus project
par: Brac University
Publié: (2023)