The engineer's observation and instruction regarding the concreting works at utility portion
This record consists of general correspondence regarding the engineer's observation and instruction regarding the concreting works at utility portion of BRAC University new campus project.
Հիմնական հեղինակ: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Ձևաչափ: | General correspondence |
Լեզու: | English |
Հրապարակվել է: |
Brac University
2023
|
Խորագրեր: | |
Առցանց հասանելիություն: | http://hdl.handle.net/10361/20367 |
Նմանատիպ նյութեր
-
The engineer's observation and instruction regarding the concreting works at utility portion
: Brac University
Հրապարակվել է: (2023) -
The engineer's observation and instruction regarding the concreting works at utility portion
: Brac University
Հրապարակվել է: (2023) -
Regarding mix design of the concrete of BRAC University new campus project
: BUCG-ABC Joint Venture (BUCG-ABC JV)
Հրապարակվել է: (2023) -
Delayed submission of check list for concreting work of BRAC University new campus project
: BUCG-ABC Joint Venture (BUCG-ABC JV)
Հրապարակվել է: (2023) -
Request to change concrete grade C10 into C15 for lean/blinding concrete
: BUCG-ABC Joint Venture
Հրապարակվել է: (2023)