Regarding the 33/11KV substation (external substation) and temporary substation (internal substation)
This record consists of general correspondence regarding the 33/11KV substation (external substation) and temporary substation (internal substation) of BRACU new campus project.
Egile nagusia: | BUCG-ABC Joint Venture (BUCG-ABC JV) |
---|---|
Formatua: | General correspondence |
Hizkuntza: | English |
Argitaratua: |
Brac University
2023
|
Gaiak: | |
Sarrera elektronikoa: | http://hdl.handle.net/10361/20268 |
Antzeko izenburuak
-
Regarding the temporary substation (internal substation) of the project
nork: BUCG-ABC Joint Venture (BUCG-ABC JV)
Argitaratua: (2023) -
Documents for temporary substation
nork: BUCG-ABC Joint Venture (BUCG-ABC JV)
Argitaratua: (2023) -
Application for the refund of the temporary substation fee returned by DESCO
nork: BUCG-ABC Joint Venture
Argitaratua: (2023) -
Request for final due payment for temporary substation work of BRAC University new campus project
nork: B-Trac Engineering Ltd.
Argitaratua: (2023) -
Instruction to start the work of substation at BRACU new campus project
nork: Brac University
Argitaratua: (2023)