Substation of claim from 26 february 2018 to 25 March 2018 due to defective fiaphragm – 04.04.18
This record consists of general correspondence regarding the substation of claim from 26 February 2018 to 25 March 2018 due to defective diaphragm of BRACU new campus development project.
Κύριος συγγραφέας: | BUCG-ABC Joint Venture |
---|---|
Μορφή: | General correspondence |
Γλώσσα: | English |
Έκδοση: |
Brac University
2023
|
Θέματα: | |
Διαθέσιμο Online: | http://hdl.handle.net/10361/20243 |
Παρόμοια τεκμήρια
-
Substation of claim from 23th April 2018 to 30th June 2018 due to defective diaphragm wall
ανά: BUCG-ABC Joint Venture
Έκδοση: (2023) -
Submission of claim from 26th March 2018 t0 22nd April 2018 due to diaphragm wall
ανά: BUCG-ABC Joint Venture (BUCG-ABC JV)
Έκδοση: (2023) -
Request of certifying compensation submitted due to defect D-wall
ανά: BUCG-ABC Joint Venture
Έκδοση: (2023) -
Payment against all claimed amount for idle time of defect in D-wall
ανά: Brac University
Έκδοση: (2023) -
Payment against all claimed amount for idle time of defect in D-wall
ανά: Brac University
Έκδοση: (2023)