Observation on delivered pipes and engineer’s instruction to arrange test from BUET
This record consists of general correspondence regarding the observation on delivered pipes and engineer’s instruction to arrange test from BUET for BRACU new campus project.
1. Verfasser: | Brac University |
---|---|
Format: | General correspondence |
Sprache: | English |
Veröffentlicht: |
Brac University
2023
|
Schlagworte: | |
Online Zugang: | http://hdl.handle.net/10361/20068 |
Ähnliche Einträge
-
Observation of BRACU on test result and visual inspection report on the fire protection and instruction to start work immediately
von: Brac University
Veröffentlicht: (2023) -
Immediate action necessary to lift the pipes that are directly placed on the floor with water contacts
von: Brac University
Veröffentlicht: (2023) -
VO #022 Extra rate of UPVC pipe changed from PVC pipe for conduit works of BRAC University new campus project
von: BUCG-ABC Joint Venture (BUCG-ABC JV)
Veröffentlicht: (2023) -
Price escalation for plumbing pipe and electricity cable works
von: Brac University
Veröffentlicht: (2023) -
Clarification of instruction