Clarification needed from Patterson Pumps (the manufacturer) regarding a major difference between the pumps ordered by BRAC University and pumps delivered by the contractor at project site
This record consists of general correspondence regarding the clarification needed from Patterson Pumps (the manufacturer) regarding a major difference between the pumps ordered by university authority and pumps delivered by the contractor at BRACU new campus project site.
1. Verfasser: | |
---|---|
Format: | General correspondence |
Sprache: | English |
Veröffentlicht: |
Brac University
2023
|
Schlagworte: | |
Online Zugang: | http://hdl.handle.net/10361/19995 |