Time extension of design change for 6th-8th floor of BRAC University new campus project
This record consists of general correspondence regarding time extension of design change for 6th-8th floor of BRAC University new campus project.
Päätekijä: | Brac University |
---|---|
Aineistotyyppi: | General correspondence |
Kieli: | English |
Julkaistu: |
Brac University
2023
|
Aiheet: | |
Linkit: | http://hdl.handle.net/10361/19727 |
Samankaltaisia teoksia
-
Time extension of design change for 6th-8th floor
Tekijä: BUCG-ABC Joint Venture (BUCG-ABC JV)
Julkaistu: (2023) -
Time extension of design change for 6th-8th floor
Tekijä: BUCG-ABC Joint Venture (BUCG-ABC JV)
Julkaistu: (2023) -
Request for time extension
Tekijä: Adex Corporation Ltd.
Julkaistu: (2023) -
Extension of time to submit quotation for carryout the works under variations or extra works
Tekijä: Brac University
Julkaistu: (2023) -
Request for time extension due to flush valve issue
Tekijä: BUCG-ABC Joint Venture (BUCG-ABC JV)
Julkaistu: (2023)