Submitting revised detailed work program
This record consists of general correspondence regarding the revised work program for supply, installation, testing and commissioning of HVAC system in BRACU new campus building.
| Main Author: | Brac University |
|---|---|
| Format: | General correspondence |
| Language: | English |
| Published: |
Brac University
2023
|
| Subjects: | |
| Online Access: | http://hdl.handle.net/10361/19608 |
Similar Items
-
Punches in the walls and slabs are being kept as per submitted drawing
by: Brac University
Published: (2023) -
Formats to be used for material, work inspection, testing and reporting for the HVAC works
by: Brac University
Published: (2023) -
Delay in completion of HVAC work at BRACU NCP
by: Brac University
Published: (2023) -
Instruction to start the work of HVAC at BRACU new campus project
by: Brac University
Published: (2023) -
Regarding proforma invoice amounts and negotiated amount of HVAC works
by: Brac University