Instruction to start the work at BRACU new campus project (Substation)
This record consists of general correspondence regarding the instruction to start the work of supply, installation, testing and commissioning of substation of BRACU new campus project.
Yazar: | Brac University |
---|---|
Materyal Türü: | General correspondence |
Dil: | English |
Baskı/Yayın Bilgisi: |
Brac University
2023
|
Konular: | |
Online Erişim: | http://hdl.handle.net/10361/19600 |
Benzer Materyaller
-
Instruction to start the work of substation at BRACU new campus project
Yazar:: Brac University
Baskı/Yayın Bilgisi: (2023) -
Regarding the temporary substation (internal substation) of the project
Yazar:: BUCG-ABC Joint Venture (BUCG-ABC JV)
Baskı/Yayın Bilgisi: (2023) -
Regarding the 33/11KV substation (external substation) and temporary substation (internal substation)
Yazar:: BUCG-ABC Joint Venture (BUCG-ABC JV)
Baskı/Yayın Bilgisi: (2023) -
Minutes of introductory meeting on supply of substation of BRACU new campus project
Yazar:: Brac University
Baskı/Yayın Bilgisi: (2023) -
Request for final due payment for temporary substation work of BRAC University new campus project
Yazar:: B-Trac Engineering Ltd.
Baskı/Yayın Bilgisi: (2023)