Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'
This record consists of general correspondence regarding approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam' of BRAC University new campus project.
Prif Awdur: | Brac University |
---|---|
Fformat: | General correspondence |
Iaith: | English |
Cyhoeddwyd: |
Brac University
2023
|
Pynciau: | |
Mynediad Ar-lein: | http://hdl.handle.net/10361/19568 |
Eitemau Tebyg
-
Rebar welding at permanent caping in D-wall
gan: Brac University
Cyhoeddwyd: (2023) -
Rebar welding at permanent caping in D-wall
gan: BUCG-ABC Joint Venture (BUCG-ABC JV)
Cyhoeddwyd: (2023) -
VO.20 - Approval of unit rates of non-schedule item rebar welding works connected to plate of steel column
gan: Brac University
Cyhoeddwyd: (2023) -
VO#20 Approval of unit rates for rebar welding works connected to plate of steel column
gan: Brac University
Cyhoeddwyd: (2023) -
Adding rebar dia 32mm welding works to vol. #20
gan: BUCG-ABC Joint Venture (BUCG-ABC JV)
Cyhoeddwyd: (2023)