Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'

This record consists of general correspondence regarding approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam' of BRAC University new campus project.

Библиографические подробности
Главный автор: Brac University
Формат: General correspondence
Язык:English
Опубликовано: Brac University 2023
Предметы:
Online-ссылка:http://hdl.handle.net/10361/19568
id 10361-19568
record_format dspace
spelling 10361-195682023-08-22T21:02:16Z Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam' Brac University New campus project General correspondence Non-schedule item Rebar welding D-wall This record consists of general correspondence regarding approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam' of BRAC University new campus project. 2023-08-22T08:44:19Z 2023-08-22T08:44:19Z ©2020 2020-01-20 General correspondence Ref. no.: BRACU-NCP/2019/006A http://hdl.handle.net/10361/19568 en This document is protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. 22 pages application/pdf Brac University
institution Brac University
collection Institutional Repository
language English
topic New campus project
General correspondence
Non-schedule item
Rebar welding
D-wall
spellingShingle New campus project
General correspondence
Non-schedule item
Rebar welding
D-wall
Brac University
Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'
description This record consists of general correspondence regarding approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam' of BRAC University new campus project.
format General correspondence
author Brac University
author_facet Brac University
author_sort Brac University
title Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'
title_short Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'
title_full Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'
title_fullStr Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'
title_full_unstemmed Approval of unit rates of non-schedule item 'Rebar Welding with Existing Rebar of D-Wall for Constructing Permanent Capping Beam'
title_sort approval of unit rates of non-schedule item 'rebar welding with existing rebar of d-wall for constructing permanent capping beam'
publisher Brac University
publishDate 2023
url http://hdl.handle.net/10361/19568
work_keys_str_mv AT bracuniversity approvalofunitratesofnonscheduleitemrebarweldingwithexistingrebarofdwallforconstructingpermanentcappingbeam
_version_ 1814307430650085376