Work order for groove cutting of Brac University new campus project
This work order has been made between Brac University and Sanjib Goldeer for groove cutting for Brac University new campus project.
Huvudupphovsman: | Brac University |
---|---|
Materialtyp: | Work order |
Språk: | English |
Publicerad: |
Brac University
2023
|
Ämnen: | |
Länkar: | http://hdl.handle.net/10361/18869 |
Liknande verk
-
Work order for groove cutting, finishing, dismantling lab floor tiles, re-plastering or install for Brac University new campus project
av: Brac University
Publicerad: (2023) -
Regarding the deviation in the groove making & pit width at north zone escalator of BRAC University new campus project
av: BUCG-ABC Joint Venture (BUCG-ABC JV)
Publicerad: (2023) -
Purchase order for supply, installation and testing of the IT floor trunk, conduit, and groove cutting in the recessed area in different floor of BracU new campus building
av: Brac University
Publicerad: (2023) -
Purchase order for supply of tiles for classroom of Brac University new campus project
av: Brac University
Publicerad: (2023) -
Purchase order for supply of tiles for classroom of Brac University new campus project
av: Brac University